Construction Progress
Live view from Beyer Hall
October 2024
- Basement sump pits/pumps, Level 1 valve tags, levels 1, 2, and 3 fixtures/fin tubes, level 4 fin tubes and restroom/shower fixtures, sound caulking throughout, dust collector
- Basement and level 1 fire alarm wire pulls, level 1 bus duct/power wire pulls/data pulls/lighting, levels 2, 3, and 4 floor boxes, levels 3 and 4 shades and lighting controls, stairwell lighting
- Level 1 paint/marker boards, level 2 ceiling tiles/restroom partitions/student lockers/transom doors/door hardware, level 3 column covers/ceiling tiles/restroom partitions, marker boards/door hardware, level 4 ceiling and border tiles/marker boards/cabinets, fume hood, folding partitions, stainless railings, industrial curtain, wood slat ceilings/walls, levels 2, 3, and 4 finish coat painting, exterior girts/insulation/metal cladding/final sealant install, roof ladders
- Curbs/gutters, asphalt, sidewalks, colored concrete/east plaza
- Elevator north car in-progress, final inspection in mid-November
- AHU/ERU controls, VAV checkout, strobic fan controls, basement metering
September 2024
- Level 1 and 4 valve tags, Level 4 grilles/registers/fin tubes/sprinkler heads, piping flush/fill/chemical treatment, strobic fan duct, level 2 and 3 restroom fixtures, sound caulking throughout
- Level 2 telecom piping, level 4 data/fire/lighting controls/lights, level 4 telecom room build-out, elevator shaft electrical, level 4 mechanical room lighting, medium voltage cabling/load testing/permanent power energize/de-energize test, set transformer and energize, level 1 fire alarm pulls/bus duct/window shades controls, levels 3 and 4 shades and lighting controls, level 2 floor boxes
- Level 2 metal doors and hardware/marker boards/polished concrete/carpet tiles/restroom tiling/cabinets, level 3 resilient flooring/metal doors and hardware/marker boards/polished concrete, level 4 ceiling grid/border tiles/storefronts/side lites, structural for wood slat walls, level 1 drywall finish, folding partitions install, exterior girts/insulation/metal cladding/window surrounds install
- Exterior column covers, light pole bases
- Elevator north car in-progress
- AHU/ERU controls, VAVs, VFD start-up testing, strobic fan controls, VAV check
August 2024
- Levels 2 and 3 fin tubes, level 4 mechanical room piping testing, AHU intake louver/louver plenum/exterior air duct install, levels 2 and 3 sprinkler heads, VFDs, levels 2, 3, and 4 grilles/registers, level 1 sound caulkin
- Level 3 lighting trim-outs/control wiring, level 4 data/fire/power pulls/lighting controls/lights, level 4 mechanical room bus duct, generator wiring, level 1 electrical room piping, elevator electrical, level 4 mechanical room lighting
- Level 2 and 3 border ceiling tiles, levels 2, 3, and 4 doors/door hardware/set storefronts/side lites, levels 2 and 3 fire extinguisher cabinets, level 2 polished concrete, levels 2 and 3 resilient flooring, level 3 and 4 ceiling grid, level 1 restroom tiles, level 2 prep for restroom tiling, exterior girts/insulation/metal cladding/window surrounds install, perforated panels
- North curb/road/service drive pours, foundation excavation for final waterproofing under curtainwall, exterior column covers, west sidewalks around new drive
- Elevator installation in-progress, south car operational
- AHU/ERU controls, VAVs, reheat system, internet switches, VFD start-up testing
July 2024
- Levels 2, 3, and 4 sound caulking/labels, level 2 fin tubes, level 2 and level 3 sprinkler heads, level 4 mechanical room piping tie-ins, level 4 VAVs/FCUs, JCI control wiring/control panels, AHU intake louver
- Level 1 can lights, level 2 lighting fixtures, level 2 and 3 trim-outs for lighting, level 3 data pulls, level 3 lighting controls, level 4 wire pulls, fire alarm pulls (all levels), wiring for shades (all levels), elevator pit wiring, generator wiring
- Installation of level 1 framing window blind pockets, level 1 shaft wall framing, level 2 ceiling grid, level 3 paint walls/door frames, overhead doors, High Bay anchor points, metal cladding east side
- Counter flash finishing on precast panels, punched window surrounds, girts for metal cladding
- Elevator installation in-progress
June 2024
- Installation of level 1 and level 4 label valves/sound caulking, level 4 mechanical piping
- Level 1 mechanical rough-ins, level 4 mechanical room rough-ins, level 2 grilles/sound caulking
- Level 1 electrical room build-out, level 1 overhead/floor box pulls, level 2 electrical trim-outs, level 3 wire pulls, fire alarm pulls (all levels), feeder pulls
- Installation of level 1 framing window blind pockets, level 1 shaft wall framing, level 2 paint walls, level 2 and level 3 prime/paint door frames, level 3 prime/paint walls
- Set glass/trim/caulk, air barrier for punched windows, metal cladding system prep
- Elevator installation in-progress
- Installation of AV screens (all levels)
May 2024
- Installation of level 1 heating water/waste pipe/vents/domestic water, precast penetrations, level 1 testing, level 3 and 4 label valves/sound caulking
- AHU/ERU under assembly, install sound attenuators, AHU/ERU sealing/flashing, level 4 overhead rough-ins, AHU/ERU filed air leak test, level 1 rough-ins
- Installation of level 4 AV/data rough-ins, elevator rough-in/wire pulls, basement level rough-ins, level 1 in-wall rough-ins, level 2 and level 3 wire pulls, wiring for temp cooling power
- Installation of level 1 framing, levels 2, 3, and 4 sound caulking walls, level 4 bulkheads, level 4 door frames, level 3 frame columns, elevator installation, level 1 bathroom partition build-out, shaft drop framing (all floors)
- Set glass/trim/caulk, air barrier for punched windows, punched window install, precast panels
April 2024
- Installation of level 1 heating water/waste pipe/vents/domestic water/storm drains, level 3 pipe insulation, level 4 compressed air/water piping, level 4 fire piping
- Installation of level 1 duct work, level 4 mechanical room duct
- Installation of basement rough-ins, level 3 feeders/electrical room/overhead rough-in/fire alarm conduit/cable trays, level 4 feeders/fire/in-wall/overhead rough-ins, level 4 electrical room build
- Installation of basement and level 1 sheetrock, level 2 insulation and sheetrock, level 3 and 4 shaft-wall framing, level 3 hollow-metal door frames, level 2 floor protection, level 2 taping/mudding
- Set curtain wall glass, trim & caulk/back pans & shadow boxes, air barrier for punched windows, window install, final foundation waterproofing, insulation behind precast
- Set switchgear/generator, splice in vault and termination to new switchgear
March 2024
- Installation of level 4 piping, shaft pipe stack clamps/anchor points, level 4 mechanical room rough-ins, level 4 plumbing/heating piping
- Installation of level 3 VAVs and rough-ins, duct insulation, level 4 duct work
- Start installation of punched windows, set curtain wall glass, air barrier for punched windows
- Installation of lightning protection ground rods, basement level in-wall rough-ins, level 2 wire pulls and AV floor boxes, overhead rough-in/fire alarm conduit
- Installation of level 1 and 3 floor/wall/door framing, level 1 vestibule framing, level 4 top outs, level 2 and 3 bathroom framing, level 3 shaft wall framing, level 4 framing
February 2024
- Installation of basement and level 3 piping, equipment tie-ins/connections, steam tie-ins/connections, shaft pipe stack clamps/anchor points
- Installation of level 3 duct/rough-ins, duct insulation, steam traps, VAVs
- Completion of water/air barrier, Installation of curtain wall, foundation trench for installation of precast panels, set curtain wall frames
- Installation of level 2 and 3 wall conduit, level 4 hangers/supports, basement and level 3 cable trays, lightning protection, level 2 feeder run
- Installation of bulkhead framing, level 1 and 4 floor grinding/floor protection, door frame blocking, level 3 floor/wall framing, level 1/vestibule framing
- Installation of elevator shaft motors
January 2024
- Installation of overhead duct work/rough-ins and duct insulation at level 3, VAV tie-ins at level 2
- Installation of wall electrical conduit at level 2 and 3, overhead electrical conduit and rough-ins at level 3
- Installation of plumbing piping at basement, level 2, and level 3, storm piping at level 3 and 4
- Installation of interior framing at basement, level 1, and level 3
- Grind level 3 floor and install floor protection
- Installation of exterior metal panels at level 1 and 2
- Firestopping installation at level 1
- Begin installation of roofing
December 2023
- Installation of level 3 partition supports
- Installation of overhead duct work/rough-ins on level 2
- Installation of overhead and wall electrical conduit on level 2
- Installation of plumbing piping at basement and level 2
- Installation of interior framing on levels 1 and 2
- Firestopping installation at level 3
- Temporary enclosure of exterior for heating, Installation of exterior metal panels at level 1
- Strobic exhaust fan delivery
November 2023
- Concrete stair pans
- Auditorium slab pours in progress
- Preparation of temporary gas line for building heat during construction
- Spray fire protection in progress for structure
- Floor protection installation for poured areas in progress
- Hanger installation in progress
- Domestic Water tie in to Thielen complete
- Preparing for AHU delivery, expect to crane to 4th floor
- Building utility tie-ins from the south in progress
- Prep for installation of air barrier/formed metal panels in progress
October 2023
- Steel frame structure erected
- Metal decking installed
- East side underground work complete
- Hangers/sleeve installation in progress
- Embeds/sleeve installation in progress
- Removal of basement bracing
- Building utility tie-ins in progress
August 2023
- Steel erection in progress
- Central core precast concrete panel work in progress (shown below)
- East and west stair precast concrete panel work in progress
- Underground storm precast work in progress
July 2023
- Basement slab and backfill are complete
- Construction on the electrical vault and installation of the stormwater detention system are in progress
- Installation of the precast concrete panels is set to begin
- Concrete work on Sheldon Avenue and Parking Lot 10 is complete; installation of retaining walls and lighting is now in progress
June 2023
May 2023
- Backfill for the elevator pit is now in progress
- Steam vault construction has begun
- Installation of formwork and pours for basement footings and walls continues (shown below)
April 2023
- Chilled water line connection to Thielen is in progress
- Excavation and installation of formwork for basement footings continues
March 2023
- Excavation for basement footings is in progress, including the elevator pit
- Chilled water line connection to Thielen in progress
- Installation of aggregate piers complete
- Backfilling for chilled water line work in progress
- Shoring in place to support existing duct bank
February 2023
- Site work on chilled water lines continues
- Preparation for installation of aggregate piers in progress
- Shoring for existing underground telecom duct bank in progress
- Sanitary sewer work on the site continues
- Sewer tie-ins to Howe Hall and Thielen Student Health Center are complete
January 2023
- Site is turned over to Story Construction
- Perimeter fencing installed, job trailers set up, and concrete demolition in progress