Live view from Howe Hall

Video Poster

Live view from Beyer Hall

Video Poster
Students riding walking and riding bikes on sidewalk with backdrop of fall leaves and new building with black exterior walls finished.

October 2024

  • Basement sump pits/pumps, Level 1 valve tags, levels 1, 2, and 3 fixtures/fin tubes, level 4 fin tubes and restroom/shower fixtures, sound caulking throughout, dust collector
  • Basement and level 1 fire alarm wire pulls, level 1 bus duct/power wire pulls/data pulls/lighting, levels 2, 3, and 4 floor boxes, levels 3 and 4 shades and lighting controls, stairwell lighting
  • Level 1 paint/marker boards, level 2 ceiling tiles/restroom partitions/student lockers/transom doors/door hardware, level 3 column covers/ceiling tiles/restroom partitions, marker boards/door hardware, level 4 ceiling and border tiles/marker boards/cabinets, fume hood, folding partitions, stainless railings, industrial curtain, wood slat ceilings/walls, levels 2, 3, and 4 finish coat painting, exterior girts/insulation/metal cladding/final sealant install, roof ladders
  • Curbs/gutters, asphalt, sidewalks, colored concrete/east plaza
  • Elevator north car in-progress, final inspection in mid-November
  • AHU/ERU controls, VAV checkout, strobic fan controls, basement metering
Men working on the southside of the building with black exterior and a boom sitting inactive in front of the building. Photo taken from outside the perimeter of the chainlink fence surrounding the building.

September 2024

  • Level 1 and 4 valve tags, Level 4 grilles/registers/fin tubes/sprinkler heads, piping flush/fill/chemical treatment, strobic fan duct, level 2 and 3 restroom fixtures, sound caulking throughout
  • Level 2 telecom piping, level 4 data/fire/lighting controls/lights, level 4 telecom room build-out, elevator shaft electrical, level 4 mechanical room lighting, medium voltage cabling/load testing/permanent power energize/de-energize test, set transformer and energize, level 1 fire alarm pulls/bus duct/window shades controls, levels 3 and 4 shades and lighting controls, level 2 floor boxes
  • Level 2 metal doors and hardware/marker boards/polished concrete/carpet tiles/restroom tiling/cabinets, level 3 resilient flooring/metal doors and hardware/marker boards/polished concrete, level 4 ceiling grid/border tiles/storefronts/side lites, structural for wood slat walls,  level 1 drywall finish, folding partitions install, exterior girts/insulation/metal cladding/window surrounds install
  • Exterior column covers, light pole bases
  • Elevator north car in-progress
  • AHU/ERU controls, VAVs, VFD start-up testing, strobic fan controls, VAV check
Exterior aerial view of the building and construction from the southwest side. Some of the black exterior has been installed on the south side of the building. The Marston water tower can be seen in the distance.

August 2024

  • Levels 2 and 3 fin tubes, level 4 mechanical room piping testing, AHU intake louver/louver plenum/exterior air duct install, levels 2 and 3 sprinkler heads, VFDs, levels 2, 3, and 4 grilles/registers, level 1 sound caulkin
  • Level 3 lighting trim-outs/control wiring, level 4 data/fire/power pulls/lighting controls/lights, level 4 mechanical room bus duct, generator wiring, level 1 electrical room piping, elevator electrical, level 4 mechanical room lighting
  • Level 2 and 3 border ceiling tiles, levels 2, 3, and 4 doors/door hardware/set storefronts/side lites, levels 2 and 3 fire extinguisher cabinets, level 2 polished concrete, levels 2 and 3 resilient flooring, level 3 and 4 ceiling grid, level 1 restroom tiles, level 2 prep for restroom tiling, exterior girts/insulation/metal cladding/window surrounds install, perforated panels
  • North curb/road/service drive pours, foundation excavation for final waterproofing under curtainwall, exterior column covers, west sidewalks around new drive
  • Elevator installation in-progress, south car operational
  • AHU/ERU controls, VAVs, reheat system, internet switches, VFD start-up testing

July 2024

  • Levels 2, 3, and 4 sound caulking/labels, level 2 fin tubes, level 2 and level 3 sprinkler heads, level 4 mechanical room piping tie-ins, level 4 VAVs/FCUs, JCI control wiring/control panels, AHU intake louver
  • Level 1 can lights, level 2 lighting fixtures, level 2 and 3 trim-outs for lighting, level 3 data pulls, level 3 lighting controls, level 4 wire pulls, fire alarm pulls (all levels), wiring for shades (all levels), elevator pit wiring, generator wiring
  • Installation of level 1 framing window blind pockets, level 1 shaft wall framing, level 2 ceiling grid, level 3 paint walls/door frames, overhead doors, High Bay anchor points, metal cladding east side
  • Counter flash finishing on precast panels, punched window surrounds, girts for metal cladding
  • Elevator installation in-progress
exterior view of construction progress on the Therkildsen Industrial Engineering building

June 2024

  • Installation of level 1 and level 4 label valves/sound caulking, level 4 mechanical piping
  • Level 1 mechanical rough-ins, level 4 mechanical room rough-ins, level 2 grilles/sound caulking
  • Level 1 electrical room build-out, level 1 overhead/floor box pulls, level 2 electrical trim-outs, level 3 wire pulls, fire alarm pulls (all levels), feeder pulls
  • Installation of level 1 framing window blind pockets, level 1 shaft wall framing, level 2 paint walls, level 2 and level 3 prime/paint door frames, level 3 prime/paint walls
  • Set glass/trim/caulk, air barrier for punched windows, metal cladding system prep
  • Elevator installation in-progress
  • Installation of AV screens (all levels)
IMSE faculty tour the construction progress of the new Therkildsen Industrial Engineering building.

May 2024

  • Installation of level 1 heating water/waste pipe/vents/domestic water, precast penetrations, level 1 testing, level 3 and 4 label valves/sound caulking
  • AHU/ERU under assembly, install sound attenuators, AHU/ERU sealing/flashing, level 4 overhead rough-ins, AHU/ERU filed air leak test, level 1 rough-ins
  • Installation of level 4 AV/data rough-ins, elevator rough-in/wire pulls, basement level rough-ins, level 1 in-wall rough-ins, level 2 and level 3 wire pulls, wiring for temp cooling power
  • Installation of level 1 framing, levels 2, 3, and 4 sound caulking walls, level 4 bulkheads, level 4 door frames, level 3 frame columns, elevator installation, level 1 bathroom partition build-out, shaft drop framing (all floors)
  • Set glass/trim/caulk, air barrier for punched windows, punched window install, precast panels
Tour group getting shown the second floor of the construction site with worker doing drywall work in the background.

April 2024

  • Installation of level 1 heating water/waste pipe/vents/domestic water/storm drains, level 3 pipe insulation, level 4 compressed air/water piping, level 4 fire piping
  • Installation of level 1 duct work, level 4 mechanical room duct
  • Installation of basement rough-ins, level 3 feeders/electrical room/overhead rough-in/fire alarm conduit/cable trays, level 4 feeders/fire/in-wall/overhead rough-ins, level 4 electrical room build
  • Installation of basement and level 1 sheetrock, level 2 insulation and sheetrock, level 3 and 4 shaft-wall framing, level 3 hollow-metal door frames, level 2 floor protection, level 2 taping/mudding
  • Set curtain wall glass, trim & caulk/back pans & shadow boxes, air barrier for punched windows, window install, final foundation waterproofing, insulation behind precast
  • Set switchgear/generator, splice in vault and termination to new switchgear

 

Construction manager talking with IMSE department member with pipes in background on construction site.

March 2024

  • Installation of level 4 piping, shaft pipe stack clamps/anchor points, level 4 mechanical room rough-ins, level 4 plumbing/heating piping
  • Installation of level 3 VAVs and rough-ins, duct insulation, level 4 duct work
  • Start installation of punched windows, set curtain wall glass, air barrier for punched windows
  • Installation of lightning protection ground rods, basement level in-wall rough-ins, level 2 wire pulls and AV floor boxes, overhead rough-in/fire alarm conduit
  • Installation of level 1 and 3 floor/wall/door framing, level 1 vestibule framing, level 4 top outs, level 2 and 3 bathroom framing, level 3 shaft wall framing, level 4 framing

 

Arlys and Denva on building construction tour

February 2024

  • Installation of basement and level 3 piping, equipment tie-ins/connections, steam tie-ins/connections, shaft pipe stack clamps/anchor points
  • Installation of level 3 duct/rough-ins, duct insulation, steam traps, VAVs
  • Completion of water/air barrier, Installation of curtain wall, foundation trench for installation of precast panels, set curtain wall frames
  • Installation of level 2 and 3 wall conduit, level 4 hangers/supports, basement and level 3 cable trays, lightning protection, level 2 feeder run
  • Installation of bulkhead framing, level 1 and 4 floor grinding/floor protection, door frame blocking, level 3 floor/wall framing, level 1/vestibule framing
  • Installation of elevator shaft motors

 

Therkildsen IE building construction, man working on concrete with orange curtains in background

January 2024

  • Installation of overhead duct work/rough-ins and duct insulation at level 3, VAV tie-ins at level 2
  • Installation of wall electrical conduit at level 2 and 3, overhead electrical conduit and rough-ins at level 3
  • Installation of plumbing piping at basement, level 2, and level 3, storm piping at level 3 and 4
  • Installation of interior framing at basement, level 1, and level 3
  • Grind level 3 floor and install floor protection
  • Installation of exterior metal panels at level 1 and 2
  • Firestopping installation at level 1
  • Begin installation of roofing

 

People in safety gear touring the Therkildsen Building construction site.

December 2023

  • Installation of level 3 partition supports
  • Installation of overhead duct work/rough-ins on level 2
  • Installation of overhead and wall electrical conduit on level 2
  • Installation of plumbing piping at basement and level 2
  • Installation of interior framing on levels 1 and 2
  • Firestopping installation at level 3
  • Temporary enclosure of exterior for heating, Installation of exterior metal panels at level 1
  • Strobic exhaust fan delivery
drone view of Therkildsen Industrial Engineeering building construction

November 2023

  • Concrete stair pans
  • Auditorium slab pours in progress
  • Preparation of temporary gas line for building heat during construction
  • Spray fire protection in progress for structure
  • Floor protection installation for poured areas in progress
  • Hanger installation in progress
  • Domestic Water tie in to Thielen complete
  • Preparing for AHU delivery, expect to crane to 4th floor
  • Building utility tie-ins from the south in progress
  • Prep for installation of air barrier/formed metal panels in progress
drone view of Therkildsen Industrial Engineering building construction
drone view of Therkildsen Industrial Engineering building construction

October 2023

  • Steel frame structure erected
  • Metal decking installed
  • East side underground work complete
  • Hangers/sleeve installation in progress
  • Embeds/sleeve installation in progress
  • Removal of basement bracing
  • Building utility tie-ins in progress
drone view of Therkildsen Industrial Engineering construction
drone view of Therkildsen Industrial Engineering building construction

August 2023

  • Steel erection in progress
  • Central core precast concrete panel work in progress (shown below)
  • East and west stair precast concrete panel work in progress
  • Underground storm precast work in progress
crane handling building components on Therkildsen Industrial Engineering building construction site

July 2023

  • Basement slab and backfill are complete
  • Construction on the electrical vault and installation of the stormwater detention system are in progress
  • Installation of the precast concrete panels is set to begin
  • Concrete work on Sheldon Avenue and Parking Lot 10 is complete; installation of retaining walls and lighting is now in progress

June 2023

drone view of Therkildsen Industrial Engineering building construction

May 2023

  • Backfill for the elevator pit is now in progress
  • Steam vault construction has begun
  • Installation of formwork and pours for basement footings and walls continues (shown below)
Therkildsen Industrial Engieering building construction
Therkildsen Industrial Engieering building construction

April 2023

  • Chilled water line connection to Thielen is in progress
  • Excavation and installation of formwork for basement footings continues
view of basement footings construction
view of basement footings construction
view of basement footings construction

March 2023

  • Excavation for basement footings is in progress, including the elevator pit
view of excavation
view of excavation
  • Chilled water line connection to Thielen in progress
  • Installation of aggregate piers complete
  • Backfilling for chilled water line work in progress
  • Shoring in place to support existing duct bank
foundation preparation begins

February 2023

  • Site work on chilled water lines continues
  • Preparation for installation of aggregate piers in progress
  • Shoring for existing underground telecom duct bank in progress
  • Sanitary sewer work on the site continues
  • Sewer tie-ins to Howe Hall and Thielen Student Health Center are complete

January 2023

  • Site is turned over to Story Construction
  • Perimeter fencing installed, job trailers set up, and concrete demolition in progress
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment
concrete demolition begins with heavy equipment